UPS, AMF, ATS and Generator Load Testing - July 2019

09 July 2019

As part of Web Wiz planned and preventative maintenance regime we will be carrying out load testing on the Uninterruptible Power Supplies (UPS), Automatic Mains Failure (AMF), Automatic Transfer Switching (ATS) and Neutral Gas Powered Generator Systems at our Data Centre.

During the test period, the UPS systems will take the full load of the Data Hall while the Generator comes online and the AMF moves the facility to Generator Power.  

The Generator will take the full load of the facility for a 20 minute period, once the test is completed power to our facility will return to our usual mix of Solar, Battery, and Utility Power.

Automatic Transfer Switching (ATS) will move rack power from "A" to "B" Power Feeds before returning each Rack to "A" Power Feeds.

At Risk period:
Start Date: 17th July 2019

Times work will be carried out:
Start Time: 08:00
End Time: 08:20

Service Impact:
No impact to services is expected.

Reason:
This routine maintenance is essential to ensure that the UPS, Generator and Automatic Switching systems work as intended and are able to provide power to our Data Centre in the unlikely event of a Power Outage.




Become a Fan on Facebook Follow us on Twitter Connect with us on LinkedIn Community Forums Web Wiz Blogs Web Wiz News
About Web Wiz | Contact Web Wiz | Terms & Conditions | Cookies | Privacy Policy

Web Wiz is the trading name of Web Wiz Ltd. Company registration No. 05977755. Registered in England and Wales.
Registered office: Web Wiz Ltd, Unit 18, The Glenmore Centre, Fancy Road, Poole, Dorset, BH12 4FB, UK.

Prices exclude VAT unless otherwise stated. VAT No. GB988999105 - $, € prices shown as a guideline only.

Copyright ©2001-2019 Web Wiz Ltd. All rights reserved.